Choose values for the preferences:
Schedule Based On. Select whether the project
is scheduled based on Estimated start/end dates
or Actual start/end dates. If set to Actual,
when actual dates are entered for a WBS task, the project schedule will
be automatically recalculated.
When set to Actual, the following behavior
occurs:
- As WBS tasks are started or completed, the actual start and finish dates
will also reflect as the estimated dates. The actual dates are copied
to the estimated fields reflecting actual dates.
- The WBS schedule is re-calculated taking into account the actual
dates which are now also reflected as estimated dates for those tasks
that are started and/or completed.
- When a task is completed, the estimated duration of the task is overwritten
reflecting the actual duration of the task taking into account the actual
start and finish dates. The duration unit is maintained when the duration
is updated to reflect actual duration.
- Tasks that are started or completed after normal working hours (for
example, before 8 AM or after 5 PM) are not counted toward the duration
and those dates are rounded to next available working hours when calculating
dependencies.
Duration Unit. From the drop-down list, choose
Days or Hours as the project's default duration unit. The unit will be
pre-selected with Days (but editable) when creating tasks. Does not show
for a task.
Send Reminder. From the drop-down list, choose
the number of days before or after the project due date that you want
reminders to be sent. If you don't want to send reminders, choose Do
not send reminder.
Recurrence Interval. From the drop-down list,
choose how often you want to send reminders after the initial reminder.
These intervals are relative to the date chosen in the Send Reminder
list. If you don't want to send reminders, choose Do not send
additional reminders. Reminders are only sent if the project
is not completed.
Effort Settings. The following items control
efforts on a project.
Effort Notifications. Select TRUE to enable
e-mail notification when efforts are submitted for approval.
Effort Submission. Select whether efforts are
submitted at the Task level or Phase
level.
Assigned Task Notification Setting. The following
items control notifications for assigned tasks.
Send Reminder.From the drop-down list, choose
the number of days before or after the task due date that you want reminders
to be sent. If you don't want to send reminders, choose Do
not send reminder.
Recurrence Interval. From the drop-down list,
choose how often you want to send reminders after the initial reminder.
These intervals are relative to the date chosen in the Send Reminder
list. If you don't want to send reminders, choose Do not send
additional reminders. Reminders are only sent if the task
is not completed.